A refund of an advance payment (zaliczka) for a service becomes an issue when a company has accepted a payment and then has not started work, keeps postponing the date or has stopped answering messages. This applies both to a renovation and to, for example, a fitted kitchen, organising a party or a photo session ordered by a private individual.

The first step is to establish whether the amount paid was an advance payment (zaliczka) or a deposit (zadatek). What can be demanded when the service provider does not perform the contract depends on that.

Opoka · KrawczykLegal position stated in the Polish source:

An advance payment or a deposit

An advance payment and a deposit are two different payments, although both are made before the service is performed. Where the contract is performed, both an advance payment and a deposit are credited towards the price. The difference appears only when one of the parties to the contract does not perform it.

The consequences of a deposit are regulated by Article 394 of the Civil Code. An advance payment is not separately regulated and is settled under the general rules. The classification of a particular payment requires assessment, so it is worth checking how it was described in the contract, in the order, in the title of the transfer and in the messages from the contractor. If these documents use different terms, it is a good idea to put them together in one note with the dates.

An advance payment after a service that was not performed

The settlement of an advance payment where the service provider has not performed the contract depends on the circumstances of the case, so its refund requires assessment against the specific documents. For example, a person ordered a fitted wardrobe and paid part of the price. The carpenter did not turn up on the agreed date and later stopped answering the phone. In such a situation it is worth collecting the documents and considering a written demand for the amount paid to be refunded.

The situation must be assessed differently where it is the client who gives up the service before it is performed. The settlement of the payment then depends on the terms of the contract and the circumstances. Such a case requires assessment against the specific documents.

Where the contractor has started work but not finished it, it is worth comparing the payments with the scope of the work actually carried out. For renovations, this is described in the guide The renovation contractor did not finish the work: what to establish .

A deposit in the case of a service

Where the parties agreed a deposit and the service provider has not performed the contract, the client may, as a rule, withdraw from the contract and demand a sum equal to double the deposit (Article 394 KC). Where it is the client who does not perform the contract, the service provider may withdraw and keep the deposit received. Before making a declaration, it is worth collecting the correspondence showing how the arrangements went and which party failed to perform the contract.

A deposit when buying a property is described in the guide Deposit when buying a flat: refund and double the amount (in Polish). The settlement of prepayments between businesses is discussed in the guide Advance payment (zaliczka) and deposit (zadatek) in a B2B contract: prepayment and settlement .

Documents and a demand for refund of the advance payment

Before sending a demand, it is worth preparing:

  • the contract, order or quotation with a description of the service and the date,
  • confirmation of payment with the date, amount and title of the transfer,
  • messages in which the contractor confirms the date, postpones it or cancels it,
  • a note of the dates the contractor was absent and of attempts to make contact,
  • invoices for additional costs incurred because the service was not performed.

It is a good idea to draw up the demand in writing. It is worth stating in it the contract, the amount paid, the date of the transfer, the demand for a refund, and the time limit and bank account number for the refund. It is best to send the demand in a way that makes it possible to prove delivery, e.g. by registered letter or to an e-mail address previously used in correspondence with the contractor.

Where non-performance of the service caused additional damage, e.g. the need to order a more expensive service from another company at short notice, Article 471 KC may be relevant. It is worth documenting each such item.

Typical difficulties in recovering an advance payment

Many cases become complicated at the stage of evidence. The contractor postpones the date several times in a phone call, and the client has no record of these arrangements. That is why each new date proposed by the service provider is worth confirming with a short message, e.g. "as agreed, the crew will start work on 12 May".

Difficulties also arise with a cash payment. If the contractor did not issue a receipt, proving the amount and the date the money was handed over later can be hard. With a cash payment, it is therefore worth asking for a receipt showing the date, the amount, a signature and a description of the service.

Correspondence with the contractor is often found only on a phone. Before changing the device or deleting a conversation, it is a good idea to save screenshots showing the dates and the sender's number. Such a compilation is useful both for the demand and in a conversation with the consumer ombudsman.

When the service provider does not respond

A consumer may ask for free help from the county or municipal consumer ombudsman (powiatowy lub miejski rzecznik konsumentów), who may approach the business. The voivodeship inspectorate of the Trade Inspection (Inspekcja Handlowa) conducts mediation and runs permanent consumer arbitration courts. A claim for refund of an advance payment can also be pursued before an ordinary court.

With each of these routes, the same compilation of documents and dates is useful. It is also worth keeping the contractor's details from the advertisement, the website or the invoice, because they make it easier to establish who the other party to the contract is.

Frequently asked questions

How to recover an advance payment for a service when the company did not come on the agreed date?

It is worth collecting the contract or messages with the arrangements, the confirmation of payment and a note of the dates. A written demand for a refund can then be sent with a time limit. Whether, and to what extent, the advance payment is refundable requires assessment in a particular case.

Can double the amount be demanded for an advance payment?

A sum equal to double the amount is a consequence of a deposit, regulated in Article 394 KC. An advance payment is not separately regulated and is settled under the general rules. Before formulating the demand, it is therefore worth establishing how to classify the payment.

What if the contract described the payment neither as an advance payment nor as a deposit?

The other documents then matter, including the title of the transfer and the parties' messages. The classification of the payment in such a situation requires assessment in a particular case, which can be asked about through the contact form (in Polish).

Related guides

Have a question about your own case?

Please briefly describe what your matter concerns. We will reply to let you know whether and how we can help. kontakt@polski-prawnik.pl

kontakt@polski-prawnik.pl

Email the firm

Sources

  • Act of 23 April 1964 – Civil Code (Journal of Laws 1964 No. 16, item 93), Article 394 and Article 471.

This material is for information and does not constitute legal advice in an individual case.