Opoka · Krawczyk
ADWOKACI

Return of tender security under the PZP: time limit for return and retention of the tender security (wadium)

Questions about the return of tender security (wadium) under the Public Procurement Law (Prawo zamówień publicznych, PZP) usually come from contractors (wykonawcy) who submitted a tender in a public procurement procedure and, after the procedure ended, did not receive their money back. A second group are firms that have been informed by the contracting authority (zamawiający) that the tender security is being retained and want to assess whether the decision is justified.

The answer depends on the course of the particular procedure, on the content of the procurement documents and on the form in which the tender security was provided. Articles 97-98 PZP set out the permitted forms of tender security, the grounds for its return and retention, and the time limits. A request for early return calls for particular caution, because it affects legal remedies.

Opoka · KrawczykLegal position stated in the Polish source:

Return of tender security under the PZP and the procedure documents

The first step is to gather the documents showing what the contracting authority required and what the contractor did. These are above all the specification of the terms of the contract, the contract notice, the tender submitted and all the explanations and amendments to the documents that arose in the course of the procedure.

Proof that the tender security was provided is worth preparing separately. For a payment of money, this will be the confirmation of the transfer with the date and the payment title. If the tender security was provided in another form, a copy of the document handed to the contracting authority will be needed, together with confirmation that it was submitted.

The third group is the correspondence with the contracting authority after the opening of the tenders. This covers requests, the contractor's replies, and information about the choice of a tender or the cancellation of the procedure. Only by putting these documents together can it be assessed at what stage the procedure ended.

Tender security in the form of a guarantee

Tender security may be provided in money, as a bank guarantee, as an insurance guarantee or as a surety specified by statute. One or several forms may be used (Article 97(7) PZP).

For a guarantee or a surety, the original of the document is handed to the contracting authority in electronic form. Return takes place by a statement of the contracting authority releasing the tender security, addressed to the guarantor or surety (Article 98(5)). It therefore does not consist of a transfer of money to the contractor.

If the guarantor has received a demand for payment, it should be kept together with its date. The content of the guarantee and the statutory basis for retention should be assessed separately.

When tender security is forfeited in a tender

Article 98(6) PZP links retention to specified situations. They include culpable failures on the contractor's part to respond to statutory requests or to consent to the correction of an identified error, where this made it impossible to choose a tender.

Retention also applies to the chosen contractor who refuses to sign the contract on the terms of the tender or does not provide the required performance bond. A further ground is the impossibility of concluding the contract for reasons lying on the side of the chosen contractor.

Not every failure to supplement a document meets all the conditions for retention. It is necessary to check the basis of the request, the reason for the omission and the effect on the possibility of making a choice. In the case of a guarantee or a surety, the contracting authority applies for payment to the relevant entity.

Time limit for return of tender security and delay by the contracting authority

The contracting authority returns the tender security without delay, and at the latest within seven days of the expiry of the tender validity period, the conclusion of the contract or the proper cancellation of the procedure. In the case of cancellation, the reservation concerning an appeal and the time limit for filing it must be taken into account (Article 98(1) PZP).

Article 98(2) also provides for return on the request of a specified contractor. This applies, among others, to the withdrawal of a tender before the deadline, its rejection, and contractors who were not chosen after the choice of a tender. In that case the seven-day period runs from the request.

Submitting a request under paragraph 2 brings about the termination of the legal relationship with the contractor and the loss of the right to the legal remedies under Part IX of the PZP. For that reason, before demanding such a return, it must be established whether the contractor intends to challenge the act (Article 98(3)).

For money, the return includes the interest earned on the account, after the statutory deduction of costs and the commission for the transfer. Where there is a dispute about retention or non-return, the appropriate remedy must be determined. An appeal under the PZP regime requires the conditions of Articles 505 and 513 to be met, as well as the time limit in Article 515. A claim for payment requires a separate assessment under civil law. The time limits and requirements for an appeal are described in the guide Rejection of a tender under the Public Procurement Law (PZP): appeal to the National Appeals Chamber (KIO) and time limits .

What to prepare before speaking to a lawyer

A contractor who is waiting for the return of the tender security or who has received information that it is being retained can gather, among others:

  • the specification of the terms of the contract, the contract notice, and the explanations and amendments to them;
  • the tender submitted, with its attachments;
  • the confirmation of the transfer, or a copy of the guarantee document and confirmation that it was submitted;
  • all the correspondence with the contracting authority, including requests and replies, with dates;
  • information about the result of the procedure or its cancellation;
  • the letter about the retention of the tender security and any correspondence with the guarantor.

The list is a guide, and the full set of documents depends on the case.

Common mistakes

  • No proof that the tender security was provided. Without the confirmation of the transfer or a copy of the guarantee, it is hard to reconstruct the course of the case.
  • Reading only the first page of the guarantee. Provisions later in the document may matter for the case.
  • Leaving a letter about the retention of the tender security without a response. It is worth recording the date of receipt at once and discussing the letter with a lawyer.
  • Arrangements made only by telephone. Written correspondence makes it possible to show later what was agreed and when.
  • Confusing a public tender with a bailiff's auction. Tender security in a bailiff's auction is a separate topic, which we do not discuss here.

Related topics

We write about what to check in a commercial contract before signing in the guide Commercial contract: what to check before signing . We write about contractual penalties in relations between businesses in the guide Contractual penalty between businesses: when it is due, a penalty for withdrawal and when a court will reduce it .

A short description of the case can be sent through the contact form (in Polish).

Frequently asked questions

Return of tender security under the PZP: where to start?

By establishing the form of the tender security and the event under Article 98 PZP that justifies its return. The seven-day time limit can then be fixed correctly. Before a request for return under paragraph 2, the consequence of losing legal remedies must be assessed.

When is tender security forfeited in a tender?

Under the statutory conditions of Article 98(6) PZP. They cover specified failures on the contractor's side that make it impossible to choose a tender, as well as a refusal to conclude the contract, failure to provide the performance bond, or the impossibility of concluding the contract for reasons attributable to the chosen contractor. Each ground requires all its conditions to be checked.

Retention of tender security: must it be accepted?

The contracting authority's decision should not be accepted without checking it, nor assumed in advance to be wrong. It is worth comparing the reasons given for the retention with the procurement documents and the tender, and discussing the next steps with a lawyer.

Tender security in the form of a guarantee: what to check?

It is worth establishing who issued the guarantee, how long it is valid and to whom it was handed. The document should be read in full and the correspondence with the guarantor kept.

What is the time limit for return of tender security?

In principle, at the latest seven days from the event indicated in Article 98(1) PZP. For return on a request under paragraph 2, it is seven days from the request. The basis for return and the effect of an appeal must be established before the date is calculated.

Related guides

Do you live abroad?

TwojaSprawa helps with matters concerning Poles living abroad. TwojaSprawa

TwojaSprawa

Have a question about your own case?

Please briefly describe what your matter concerns. We will reply to let you know whether and how we can help. kontakt@polski-prawnik.pl

kontakt@polski-prawnik.pl

Email the firm

Sources

The state of the sources was checked on 15 November 2026.

This material is for information and does not constitute legal advice in an individual case.