Opoka · Krawczyk
ADWOKACI

Force majeure in a contract: how to document an interruption in delivery

Force majeure in a commercial contract becomes the subject of a dispute when a delivery does not arrive on time and the counterparties explain the cause of the delay differently. The closure of the road to the plant may have prevented a prepared consignment from leaving. It may also have happened after the day on which the goods should already have left the warehouse. To assess both situations the agreed schedule, the content of the contract and the actual course of the delivery are needed.

The guide describes how to organise the facts and documents after a disruption to a delivery. Whether a particular event amounts to force majeure, and what effects it has on the time limit and on liability, requires an assessment in the particular case.

Opoka · KrawczykLegal position stated in the Polish source:

An obstacle affecting a specific order

For example, a steelworks was to deliver sheets of metal to a manufacturer's hall. After flooding, the road by the loading gate was closed. For the assessment, the time the road was closed, the carrier's planned collection and information on when the sheets were ready will be useful. A notice about flooding across the whole municipality tells less about this delivery than data about the road the carrier actually used.

Not every difficulty with a delivery has the same significance. An ordinary organisational difficulty or an earlier delay by the supplier may be assessed differently from an obstacle that actually made a specific performance impossible. The foreseeability of the event and the available substitute solutions may also matter. The name of an event alone, for example flooding, does not decide how it will be assessed.

It is also worth establishing whether the event affected the whole order. If part of the goods was already in an external warehouse, the documents on the closed gate must be tied to the specific consignment. The customer may have been waiting above all for sheets of one thickness, while being able to use another part of the order later.

It is good to add to the gathered information what was not yet known at the time of the event. The first notice may have anticipated the road reopening in the afternoon, the next only the following day. Keeping both makes it possible to explain why the first message addressed to the customer gave a different expected delivery time from the next.

Force majeure and a delay that was already under way: a chronology of events

It is worth starting the chronology from the moment when performance was still going according to plan. If the sheets were to be ready before the road closure, it must be established whether production was in fact completed and collection agreed with the carrier. It may turn out that the earlier date was entered only in a working plan, and the customer then accepted a different date.

It also happens that the order was already waiting for a missing raw material before the flooding. It is then good to set out the earlier interruption and the road obstructions as separate events. Attributing all the days of delay to one cause will make it harder to assess the link between the event and the non-performance of the given obligation. The general steps on the ordering party's side are described in the guide Counterparty's failure to perform a contract: a company's first steps .

Liability for non-performance of a contract in the Civil Code

The general principle of liability for loss resulting from non-performance or improper performance of an obligation is expressed in Article 471 of the Act of 23 April 1964 – Civil Code (KC). The debtor is liable for such loss unless the non-performance or improper performance resulted from circumstances for which the debtor is not liable. This provision concerns compensation for loss and does not contain a definition of force majeure. The assessment requires establishing which party bore the risk of the given event, whether there was a link between the event and the non-performance, and what evidence there is of it.

The contract may provide that the debtor takes on liability for specified circumstances for which the statute does not make the debtor liable (Article 473 § 1 KC). The significance of an event must therefore also be assessed against the background of the agreed contract. Where a counterparty demands a contractual penalty for delay, the rules for pursuing it are discussed in the guide Contractual penalty between businesses: when it is due, a penalty for withdrawal and when a court will reduce it .

A force majeure clause in the parties' documents

It is worth finding the exact passage of the contract that describes events hindering performance. If a clause refers to general terms of delivery, the correct version of them will be needed for the analysis. In these documents you can mark separately the description of the event, the duties to give information and what the parties provided for the further performance of orders. Whether the list of events is closed and what effects the manner, the time limit or the absence of notice has requires an analysis of the particular contract.

In a conversation about a draft contract, one real order described from acceptance through to collection is useful. It makes it possible to check who will be the first to receive information about the obstacle and which data that employee will be able to provide. A dispatcher can confirm the closure of the gate at once, but the assessment of the condition of the goods will be given only by the warehouse once it gains access to the hall.

If the draft names one address for notices, it is good to compare it with the addresses actually used by the purchasing and transport departments. Before signing, you can establish who receives such a letter and where further information is recorded. The documents and questions when concluding a contract are discussed in the guide Commercial contract: what to check before signing .

Information for the customer and resumption of deliveries

For an event that has already happened, copies of messages sent to the counterparty, the times they were sent and the replies kept are useful. If the customer received only a telephone call from the driver, it is worth reconstructing who spoke and what the conversation concerned. Whether such contact met the requirements written into the contract needs separate checking.

After the road is opened, other obstacles may remain. A flooded warehouse may need to be checked, a vehicle may have been assigned to another job, and the buyer may in the meantime have changed the available unloading hours. It is therefore worth separating the date the event itself ended from the moment the given consignment could actually leave and reach the customer.

Where part of the order was carried out by another route, it is worth keeping the carrier's proposal and the documents of that delivery. Information about solutions that were considered and rejected, and the specific reasons for that decision, is also useful. A photograph of a flooded road alone will not show, for example, that the second access had a height restriction that ruled out a vehicle with that load.

If after the event the parties wish to change deadlines or delivery terms permanently, this is a separate matter that requires a separate assessment. How to prepare such a change is described in the guide An annex (aneks) to a commercial contract: how to prepare a change of terms .

Establishing the facts after an interruption in delivery

  1. The orderIt is worth identifying the consignment of goods, the agreed deadline and the state of performance immediately before the obstacle arose.
  2. The eventMessages and documents relating to the specific place should be compared with the dates of production and dispatch.
  3. The contract and messagesThe full clause must be compared with the content of the information sent, its addressees and the counterparty's replies.
  4. Further performanceData on the available solutions, the restoration of access and the actual collection of individual consignments will be useful.

Frequently asked questions

How should I read a force majeure clause in a contract for the delivery of goods?

For the assessment, the full clause, the order document and a description of the event's effect on this particular delivery are needed. If the parties used an illustrative list of events in the contract, it is worth keeping also the introductory sentence and the provisions that follow the list. A single item from the list may not reflect the content of the whole clause.

How can I document the impossibility of reaching a warehouse?

Notices about the specific road, information from the carrier and the time of the agreed collection will be useful. It is worth establishing whether there was another access suitable for the given vehicle. Where there are several warehouses, you should state where the consignment corresponding to the order was located.

What should I check where, after notice of an event, the parties dispute the delivery date?

First it should be established what the message concerned and how the contract describes its effects. The message alone does not yet mean that the parties have agreed a new date. A postponement of the time limit, temporary or permanent impossibility of performance, liability for loss and a possible amendment of the contract each require separate assessment. The terms of individual orders in an ongoing business relationship are discussed in the guide B2B cooperation agreement: what it should contain and which provisions govern it .

Force majeure in a contract – what should I prepare where a counterparty attributes the whole delay to it?

It is good to compare the plan of the delivery concerned with its actual course before that event. For each period of time the source of the information and a description of which actions were then possible are useful. A discussion of a draft or of the content of an existing clause falls within the help described on the page Commercial contracts (in Polish).

Related services

Related guides

Do you live abroad?

TwojaSprawa helps with matters concerning Poles living abroad. TwojaSprawa

TwojaSprawa

Have a question about your own case?

Please briefly describe what your matter concerns. We will reply to let you know whether and how we can help. kontakt@polski-prawnik.pl

kontakt@polski-prawnik.pl

Email the firm

Sources

  • Act of 23 April 1964 – Civil Code, Article 471 and Article 473 § 1. The provisions concern the general rules of liability. The example of a hindered delivery illustrates how events can be reconstructed.

This material is for information and does not constitute legal advice in an individual case.