Explanations of an abnormally low price: calculation and evidence

Explanations of an abnormally low price (rażąco niska cena) are prepared by a contractor who has received from the contracting authority (zamawiający) a letter asking it to explain the price of its tender. The reply is based on figures the company worked out earlier, when preparing the tender.

We describe the practical side of such a reply: how to read the request, how to reconstruct the calculation and which documents a company usually uses to support it. Article 224 of the Public Procurement Law (PZP) sets out the grounds for the request, the burden of showing the price and the consequence of insufficient explanations. The time limit for the reply cannot be assumed without checking the contracting authority's request.

Opoka · KrawczykLegal position stated in the Polish source:

A request to explain the price: where to start

The contracting authority demands explanations and evidence if the price, the cost or significant components appear abnormally low or raise doubts about performance of the contract. The condition is an assessment of the particular tender against the requirements of the contract (Article 224(1) PZP).

Where the total price is at least 30% lower than the statutory reference point, Article 224(2) provides additional rules for the request. They cover the value of the contract including VAT or an average of the tenders calculated accordingly. An exception applies to obvious discrepancies that do not require explanation. This does not mean that every price below that threshold is automatically abnormally low.

The statute does not set one fixed time limit for the reply for all requests. The time limit is set by the contracting authority. The date of delivery should be kept and each question written out, so that the explanations together with the evidence arrive within the required time.

The burden of showing that the tender does not contain an abnormally low price or cost lies on the contractor. A failure to reply within the time limit, or explanations that together with the evidence do not justify the price, lead to rejection under Article 224(5)–(6) PZP.

How to reconstruct the tender calculation

The tender price is the sum of costs and the assumed profit. Explaining the price therefore consists in practice in showing what costs it is made up of and what assumptions were adopted in calculating them.

If the company has a spreadsheet from the stage of preparing the tender, it should be found in the version on the basis of which the tender was submitted. Later changes in the spreadsheet are worth describing separately, so as not to mix the original calculation with new calculations.

Where the calculation was not written down, it must be reconstructed from the documents of that period. A summary of cost items helps with this, for example:

  • materials and deliveries, with quantities and unit prices;
  • subcontractors' work, with scope and price;
  • the costs of the company's own employees, with the number of people, working time and rates;
  • equipment, transport, site facilities and other direct costs;
  • the company's overheads assigned to the contract;
  • the assumed profit, or information that the company knowingly adopted a low margin and for what reason.

For each item it is good to write down the source of the figure, for example a specific supplier's offer, a price list or data from an earlier project. This makes it easier to select attachments and to check the consistency of the whole letter.

Evidence for the price explanations: which documents to gather

An explanation without documents is hard to verify. For each significant item of the calculation it is therefore worth attaching a document that confirms it. Most often these are:

  • offers from suppliers and subcontractors, with the date and scope;
  • price lists, discounts and commercial terms agreed with regular counterparties;
  • framework agreements or earlier agreements from which the prices of materials or services result;
  • a calculation of labour costs, with the number of people, working time and rates adopted;
  • data from similar contracts carried out earlier, for example actual time of performance and costs;
  • a description of solutions that lower cost, for example own equipment, the proximity of a base or the technology adopted.

The documents should relate to this contract or refer clearly to its scope. A subcontractor's offer for a different scope of work, or a price list from several years ago, may raise doubts as to whether it supports the particular item. Which document matters in a given case and how to present it is worth discussing with a lawyer.

Some documents contain commercial data that the company does not want to reveal to competitors, for example suppliers' prices or margins. Whether and how they can be protected in the procedure requires an assessment by a lawyer before the letter is filed.

Confidentiality of the explanations and an appeal

The procedure is open. To protect a business secret, when providing information the contractor must reserve non-disclosure and show that the information meets the statutory conditions of a secret (Article 18(3) PZP). Merely marking the whole letter "confidential" does not replace a justification. Information listed in Article 222(5) cannot be reserved.

An act of rejection, or an omission, that is contrary to the statute can be challenged by an appeal where the conditions of Articles 505 and 513 PZP are met. Where electronic notice of the act is given, the rule is 10 days once the EU thresholds are reached or 5 days below them. Another method of delivery and other objects of challenge have the time limits of Article 515. The details are described in the guide on an appeal to the KIO .

Price explanations step by step

  1. Reading the requestWriting down the date of delivery, the time limit stated in the letter and each of the contracting authority's questions as a separate point.
  2. Reconstructing the calculationA summary of the cost items and assumptions from which the tender price resulted, with the source of each figure.
  3. Gathering documentsOffers from suppliers and subcontractors, price lists, agreements and calculations of labour costs relating to this contract.
  4. The letter with the explanationsAn answer to each question in the order of the request, with references to specific attachments.
  5. A check before filingChecking the consistency of the figures and the completeness of the attachments, and keeping the confirmation that the letter was filed.

What the letter with the explanations should contain

The letter is clearer when it answers the questions in the same order in which the contracting authority put them. For each answer it is worth stating the amount, the way it is calculated and the number of the attachment that confirms it.

At the beginning of the letter it is good to give the reference of the procedure and the date of the request, and at the end a list of attachments. General assurances about the company's experience will not replace calculations, although they may supplement them with a description of where the lower cost comes from.

Before filing, the figures in the letter should be compared with the tender form and with the calculation. A discrepancy between the sum of the items and the tender price, even one resulting from rounding, requires an explanation in the text of the letter.

The price explanations and the future contract

A calculation prepared for the purposes of the explanations also shows whether the company will be able to perform the contract for the price offered. It is worth taking the opportunity to read the draft contract again, especially the provisions on time limits and contractual penalties.

A contractual penalty relates to non-monetary obligations, for example time or quality of performance (Article 483 § 1 of the Polish Civil Code, "KC"). It is due in the stipulated amount irrespective of the amount of the loss (Article 484 § 1 KC). We write about this at greater length in the guide Contractual penalty between businesses: when it is due, a penalty for withdrawal and when a court will reduce it . The general rules for reading a contract before signing are described in the guide Commercial contract: what to check before signing .

What to prepare before speaking to a lawyer

Before the conversation it is worth gathering:

  • the contracting authority's request with the date of delivery;
  • the tender submitted, together with the price form and the cost estimate, if one was required;
  • the calculation from the stage of preparing the tender, or a reconstructed version of it;
  • offers from suppliers and subcontractors, price lists and agreements on which the prices were based;
  • the documentation of the procedure received from the contracting authority.

How to organise facts and questions before the meeting is described in the guide How to organise information before a conversation (in Polish).

Common mistakes

  • A general answer instead of calculations. An assurance that the price is realistic does not show what it is made up of.
  • Leaving out one of the contracting authority's questions. Organising the letter according to the questions in the request helps to avoid this.
  • Inconsistent figures. The sum of the calculation items should agree with the tender price.
  • Documents unrelated to the contract. A price list or an offer for a different scope does not support a specific item.
  • Starting work late. Gathering offers from suppliers and subcontractors takes time, so it is worth starting on the day the request is delivered.

Frequently asked questions

What should explanations of an abnormally low price contain?

In practical terms the letter answers each of the contracting authority's questions in the order of the request. For each answer it gives the amount, the way it is calculated and the attachment that confirms it. Whether such explanations are sufficient in a particular procedure is assessed by a lawyer.

What evidence should be attached to the price explanations?

These are usually offers from suppliers and subcontractors, price lists, agreements, calculations of labour costs and data from similar projects. The documents should relate to this contract or refer clearly to its scope.

How much time is there for explanations of an abnormally low price?

The time limit set by the contracting authority in the request applies. Article 224 PZP does not give one fixed number of days for all cases. A failure to provide explanations within that time limit may lead to the tender being rejected.

A tender rejected because of an abnormally low price: what then?

The justification must be compared with the explanations and the evidence. Where the conditions of Articles 505 and 513 PZP are met, an appeal can be lodged. For electronic notice of the act the rule is 10 days for a contract at or above the EU thresholds or 5 days below the thresholds.

Must the suppliers' prices be disclosed in the explanations?

The evidence may be necessary to show the price. Its confidentiality requires both reserving non-disclosure and showing the conditions of a business secret. Data excluded from protection in Article 18(3) PZP cannot be reserved.

Where can I send a description of a matter concerning price explanations?

A short description of the matter, with the date of delivery of the request, can be sent through the contact form (in Polish).

Related guides

Do you live abroad?

TwojaSprawa helps with matters concerning Poles living abroad. TwojaSprawa

TwojaSprawa

Have a question about your own case?

Please briefly describe what your matter concerns. We will reply to let you know whether and how we can help. kontakt@polski-prawnik.pl

kontakt@polski-prawnik.pl

Email the firm

Sources

The state of the sources was checked on 15 November 2026.

This material is for information and does not constitute legal advice in an individual case.