What a framework agreement is
In practice, a framework agreement is concluded where the parties expect recurring deliveries or services but on the day of signing do not yet know their quantities or dates. The framework agreement organises what is to be common to all transactions. The specific scope, quantity and date are determined only by the order or a separate implementing contract.
The name of the document does not decide its effects. In a dispute, a contract is interpreted according to the parties' common intention and the purpose of the contract, and not merely according to its literal wording (Article 65 § 2 KC). For that reason, besides the agreement itself, the correspondence from the negotiations and the way the parties actually placed and carried out orders may matter.
A framework agreement is not the same as a cooperation agreement, although the two documents are often combined. The elements of a cooperation agreement, such as the scope of performances, confidentiality or classification as a contract of mandate (zlecenie) or a contract for a specific work (umowa o dzieło), are discussed in the guide B2B cooperation agreement: what it should contain and which provisions govern it .
Whether a framework agreement is binding
A framework agreement is a contract, so the parties are bound by what they have actually agreed in it. If the framework agreement sets, for example, a price list, a payment deadline, rules on complaints or confidentiality, those provisions may matter for every order placed under it.
A different question is whether the framework agreement obliges either party to place orders or to accept them. Many framework agreements merely set the terms in case an order is placed. Others provide, for example, for minimum quantities, guaranteed production capacity or an obligation to fulfil every order within a specified limit. Where the agreement does not expressly resolve this, its meaning is assessed on the basis of the entire content of the document and the conduct of the parties.
A framework agreement and a preliminary agreement
A framework agreement is sometimes confused with a preliminary agreement. A preliminary agreement is one in which the parties undertake to conclude a specified contract in the future, and it should set out the essential provisions of the promised contract (Article 389 KC). Whether a particular framework agreement contains such an undertaking depends on its content and requires assessment by a lawyer (adwokat). We write more about the preliminary agreement in the guide Commercial contract: what to check before signing .
A framework agreement, an implementing contract and an order
An implementing contract, often called an order, an individual commission or a specification, concerns a specific transaction. It sets, among other things, the quantity, the date, the place of performance and the price, if the framework agreement refers to a price list or an individual quotation. The remaining matters, for example the rules of acceptance or liability, may follow from the framework agreement.
A declaration of intent is an offer if it sets out the essential provisions of the contract (Article 66 § 1 KC). An order placed under a framework agreement often meets that condition, and the implementing contract comes into being only once it is accepted. In case of doubt, the contract is considered concluded at the moment when the person making the offer received the declaration of acceptance (Article 70 § 1 KC).
No reply to an order
In continuing cooperation, the provision on a business's silence is particularly important. Where a business receives, from a person with whom it is in continuing business relations, an offer to conclude a contract within the scope of its activity, the absence of an immediate reply is regarded as acceptance of the offer (Article 68² KC). For that reason it is worth stating in the framework agreement a time limit for confirming or rejecting an order and the effect of failing to reply.
Between businesses, a reply to an order with changes that do not materially alter its content may be treated as acceptance of it (Article 68¹ KC). Similarly, a confirmation letter (pismo potwierdzające) concerning a contract concluded without written form may be binding if the other party does not object immediately (Article 77¹ KC). We describe both mechanisms more fully in the guide Commercial contract: what to check before signing .
A framework agreement and an ordinary one-off contract
An ordinary contract, for example a one-off sale or service, contains all the arrangements in one document and concerns one transaction. A framework agreement covers many transactions, often for a period not determined in advance, and works only together with the successive orders.
A practical difference follows from this. With a one-off contract, a dispute usually concerns a single document. With a framework agreement, it is necessary to establish which of several documents decides a given matter and whether a change of terms in one order also applies to the following ones.
What a framework agreement should contain
The provisions of a framework agreement depend on the sector and the type of performances, which is why we do not publish a model contract. In practice, a framework agreement between businesses usually settles the following:
- the subject of the cooperation and whether it covers deliveries, services or both kinds of performance;
- the way orders are placed, their minimum content, the time limit for confirmation and the effect of failing to reply;
- whether there is an obligation to place or accept orders, for example minimum quantities or limits;
- prices or the way they are set, the rules for changing the price list and the payment deadline;
- the terms of delivery, acceptance and complaints;
- the order in which the documents apply: the framework agreement, orders, attachments and general terms;
- contractual penalties and the rules of liability;
- confidentiality and, if the parties want it, exclusivity;
- duration, termination and the fate of orders in progress after the agreement ends;
- the court competent for disputes and, with a foreign counterparty, also the governing law.
The payment deadline in transactions between businesses is limited by the provisions of the Act on Counteracting Excessive Delays in Commercial Transactions. We describe them in the guide Compensation for debt-recovery costs and interest (in Polish). The rules for stipulating and reducing contractual penalties are discussed in the guide Contractual penalty between businesses: when it is due, a penalty for withdrawal and when a court will reduce it .
Order of precedence of documents and general terms
With a framework agreement, the parties usually use several documents at once. If the agreement does not set their order, a conflict between the framework agreement and an order may lead to a dispute about which provision applies. It is therefore worth stating expressly whether an order may change the framework terms and, if so, to what extent and in what form.
For general terms, the statute provides its own rules, including for the case of conflicting standard terms of the two parties (Article 385 § 1 and Article 385⁴ KC). We describe them in the guide Commercial contract: what to check before signing . A conflict between standard terms arises, for example, where the customer attaches its own general terms of purchase to its orders and the supplier accepts orders relying on its own general terms of sale.
A framework agreement with a subcontractor
A framework agreement is often concluded with a subcontractor who is to carry out part of the work for several successive commissions. Towards its own customer, the contractor is liable for the acts and omissions of the persons through whom it performs the obligation as for its own (Article 474 KC). The terms of the framework agreement with a subcontractor should therefore be compared with the contract concluded with the customer, especially the deadlines, the standard of performance, contractual penalties and the rules of acceptance.
Ending a framework agreement
A framework agreement is concluded for a fixed or an indefinite period. The rules on its termination depend on this, and we describe them in the guide Termination of a B2B contract or withdrawal: when and how . If the framework agreement was concluded in written, documentary or electronic form, terminating it requires at least documentary form (forma dokumentowa), unless a statute or the contract stipulates another form (Article 77 § 2 KC).
With a framework agreement, it is also necessary to establish what happens to orders accepted before it ended. The agreement may provide that such orders are performed on the existing terms, or that they expire together with the framework agreement. Where the agreement does not resolve this, the assessment depends on the content of the documents and the circumstances.
A framework agreement and orders step by step
- Framework agreementThe parties settle the standing terms of cooperation, the way orders are placed and the order in which documents apply.
- OrderThe customer places an order with the essential provisions of the specific transaction. Such an order is often an offer.
- ConfirmationThe contractor accepts or rejects the order. In continuing business relations, the absence of an immediate reply is regarded as acceptance of the offer.
- Performance and settlementThe parties perform the implementing contract on the terms of the order and the framework agreement.
- EndingThe framework agreement is terminated in accordance with its content. The fate of orders in progress must also be determined.
Common mistakes
- No rules for accepting orders. In continuing cooperation, the absence of an immediate reply to an order may be regarded as acceptance of it (Article 68² KC).
- An unclear obligation to order. Where the agreement does not say expressly whether orders are mandatory, the parties may understand its effects differently.
- No order of precedence of documents. A conflict between the framework agreement, the order and the general terms may lead to a dispute over what applies.
- A change of terms in a single order. Without a provision on the form and scope of changes, it is not clear whether a new price or date concerns only that order or also the following ones.
- Overlooking orders in progress. The framework agreement does not settle what happens to accepted orders after it is terminated.
- Inconsistency with the customer contract. The framework terms with a subcontractor do not match the deadlines and penalties in the contract concluded with the customer.
Which documents to prepare for a conversation with a lawyer
- a draft framework agreement with its attachments, the price list and an order template;
- the general terms of both parties, if the agreement refers to them, together with information on when they were delivered;
- sample orders and confirmations, if the cooperation is already under way;
- the correspondence from the negotiations;
- the contract with the customer, where the framework agreement concerns subcontracting.
In the conversation, it is worth asking whether the agreement imposes an obligation to place or accept orders, when an order becomes binding and how to end the cooperation without a dispute over orders in progress. Preparing for a first conversation is made easier by the guide How to prepare for a conversation with a lawyer (in Polish).
Where businesses want to change the terms of a contract that is already in force, rather than merely place further orders, the guide An annex (aneks) to a commercial contract: how to prepare a change of terms will be useful.