Subcontract for construction works: acceptance and payment

A subcontract should make it possible to establish who commissions a specific part of the works, who accepts it and with whom the subcontractor agrees payment. On one site, technical instructions, acceptance of the work and settlement of the remuneration may involve different people. Before the works begin, it is good to assign each of them a defined role and check that it is described in the same way in the contract and in the annexes.

This guide concerns domestic contracts between businesses, without public procurement. The conditions under which an investor may be liable for a subcontractor's remuneration require a separate assessment of the particular investment.

Opoka · KrawczykLegal position stated in the Polish source:

The contract with the contractor and the investor's involvement

It is good to start the conversation by naming the parties. A subcontractor may negotiate with the contractor, although the work will be carried out on the investor's premises. In the order it is worth entering the full details of the commissioning party, the scope of the works entrusted and the person with whom their progress can be agreed. It must also be checked who can sign the contract on behalf of each company, which is discussed in the guide Who can sign a contract on behalf of a company: how to check .

For a larger investment, the scope of work can be related to the design and to an identified part of the building. In pricing and in the later acceptance, the same version of the documentation should be used. If a new drawing appeared during the negotiations, it is good to establish whether it replaces the previous one entirely or changes only an indicated part. The legal classification of a given order may require an assessment of both the content of the contract and the type of works. Neither the design nor the name of the works settles it alone.

From the contractor's perspective, Article 474 KC matters. A contractor is liable to its counterparty for the actions of persons with whose help it performs the obligation as for its own actions. This also applies to the use of subcontractors. That provision concerns the relationship between the contractor and its counterparty and does not itself decide whether a subcontractor can demand payment from the investor. That second question requires a separate assessment.

The limits of the works and preparing the workplace

Disputes over settlement can often be understood only after setting a drawing beside the description of the order. When installing doors, delivering the leaves involves different activities from fitting the frames, and again different ones from finishing the openings after the work. It is worth establishing which activities a given company performs and what the previous crew is to make available to it.

The description of the works should also make it possible to price the task. For a subcontractor, the number of elements, the place of storage, access to rooms and the order in which floors are released matter. The contractor is interested in whether, after installation is finished, it can begin the next stage straight away. Such arrangements can be tied to a specific item of the schedule.

The scope excluded from the price and the way additional works are agreed should also be identified. Where someone on site proposes a change, it will help to know who raised it, on which drawing it was marked and what part of the pricing has to be agreed again. This makes it easier to reconstruct the arrangements of the two companies once a given stage is completed.

Acceptance of subcontracted works

When planning acceptance, it is good to state who reports the completion of the works, who carries out the check and against what documentation the result is compared. Works visible only before they are covered up can be provided for in the schedule as a separate inspection point. The parties can also agree in advance how comments and the re-checking of a given part will be recorded.

The protocol should make it possible to recognise the part of the works it concerns. The name of the investment alone will explain little if the company worked in several buildings at the same time. The designation of the room or section, the date of the inspection, a reference to the drawing and a description of the difference found will help. In a later settlement it is then easier to establish whether the comments concerned the whole stage or one element.

A person taking part in acceptance may hold a particular technical function on the site. Taking part in acceptance and holding a technical function need not, however, mean authority to order additional works. Before financial arrangements are accepted, it must be checked who, under the documents, can approve a change of scope or price. The name under the description of the inspection should be compared with the details of the person named in the contract for such arrangements.

For installation works, a drawing can be attached to the protocol marking the section of the line that was checked before it was covered. If a second section is to be checked the following week, it is good to give it a separate designation. When the whole installation is settled, it will then be clear to which part each comment relates.

Payment and documents concerning the investor

In the contract, it is worth linking the agreed amount with the description of the works and stating the payment deadline. For settlement by stages, it is good to prepare a list of acceptances and of the amounts due for the individual parts. It can separate the remuneration under the original order from the value of a change agreed later. Each entry should be comparable with a specific invoice and a document confirming performance.

If a subcontractor is considering applying to the investor for payment, a separate set of documents is needed. It must be established what information about the company and the scope of its works was given to the investor, who gave it and when. The reply or objection should also be kept, if they were submitted. Assessing whether the investor is liable for payment requires an examination of the circumstances of the particular investment.

Similarly, an investor to whom a subcontractor has turned can organise the letters by date. The works named in the demand are best compared with the documentation the investor received earlier. It must then be established what amount has already been paid, to whom and for which part of the works. This prevents a demand for one stage from being compared with the settlement of another.

Preparing and settling a subcontract order

  1. Parties and scopeThe details of the contractor and the subcontractor should be compared, and the part of the works identified in the design or in an annex.
  2. AcceptanceThe parties agree the date, the criteria and the person carrying out the check. It is worth stating how comments are to be reported.
  3. PaymentThe contract describes how the remuneration is determined and the payment deadline. For subsequent stages, it is worth assigning amounts to the works.
  4. DocumentationThe offer, the agreed annexes and the correspondence should be compared with the protocols and the confirmations of payments.

Frequently asked questions

What should a subcontract for one part of a building cover?

The building, the scope of works, the version of the design, the order in which rooms are released and the acceptance criteria should be identified. If part of the works is carried out by another crew, it is good to describe the point at which one task ends and the other begins. The general rules are described in the guide B2B cooperation agreement: what it should contain and which provisions govern it .

What documents to gather when the investor's consent to a subcontractor comes up in the talks?

Before the parties accept that such consent is needed or that it has been given, the exact content of the letters sent to the investor, the attachments, the proof of delivery and the investor's reply must be gathered. The significance of that correspondence and the conditions of the investor's liability for payment require an individual assessment. When commissioning it, it is also good to state the date of the contract and the dates on which the works it covers were carried out.

How to compare an acceptance protocol with the subcontractor's invoice?

The easiest way is to set the two items side by side by location and stage of the works. If the invoice covers several sections, a short breakdown can be drawn up and the relevant protocol assigned to each item. Where there were comments on the performance, it is also good to keep the document of the re-check of the works.

What to check when the contractor wants to bring in another company?

First, read the provisions on whether other contractors may be used and determine what scope of work the further company would take over. Whether a further company may be brought in is a different matter from liability for the remuneration of a further subcontractor, which requires a separate assessment. Before signing the contract, you can use the guide Commercial contract: what to check before signing . The preparation and checking of a draft is covered by the service Commercial contracts (in Polish).

Related services

Related guides

Do you live abroad?

TwojaSprawa helps with matters concerning Poles living abroad. TwojaSprawa

TwojaSprawa

Have a question about your own case?

Please briefly describe what your matter concerns. We will reply to let you know whether and how we can help. kontakt@polski-prawnik.pl

kontakt@polski-prawnik.pl

Email the firm

Sources

  • Act of 23 April 1964 – Polish Civil Code, Article 474.

This material is for information and does not constitute legal advice in an individual case.